After Action Review Process
全文音频:
Tip:单击查看句义;划选/双击查生词

[01:13.38]In the last lecture, we looked at managing a project to completion.
[01:18.06]Today, we're going to be looking at a way of judging just how successful your project has been.
[01:23.86]It's called the after action review process.
[01:27.94]A typical project review is completed long after the project is finished.
[01:32.74]And so it's too late to change the outcome.
[01:36.06]Wouldn't it be better to evaluate it along the way?
[01:39.46]So you can learn from your mistakes at each stage and improve on them.
[01:44.40]It was for this reason that the army devised the after action review process as a way for everyone to learn quickly from experiences in the field.
[01:54.36]Okay.
[01:54.92]So what are the benefits of using an after action review?
[01:59.32]Firstly, it's not just limited to very large or very formal projects, but is useful for all sorts of things.
[02:06.83]For example, you may want to use it to debrief following a staff meeting, or any other regular operational function.
[02:15.19]In the same manner, it's an extremely effective tool to use following a safety incident, and can reveal important lessons so that accidents can be avoided in the future.
[02:26.51]So you can see that this would definitely be a positive step for any business.
[02:31.71]An added benefit of the review is that because the focus is on learning, it really improves communication within working groups.
[02:40.89]So let's have a look at what an after action review is.
[02:45.15]It's a structured session or meeting that does the following.
[02:49.63]It focuses on the resulting outcomes and the reasons for these.
[02:54.47]It encourages active participation among the team, and very importantly, emphasizes how vital it is for the team to trust one another.
[03:08.39]Here are some of the key elements to remember for when you're conducting an after action review.
[03:14.34]Where possible, it's really good to have an external person to facilitate the process.
[03:20.82]This helps to direct the discussion and can also prevent a stronger member of the review from dominating the others.
[03:28.47]Make sure that you encourage active involvement.
[03:31.55]Often shy members won't say anything.
[03:34.35]So one way to encourage them to get involved is to ask people to put their comments in writing.
[03:41.00]If they aren't given the opportunity to do this, they may be intimidated by other members of the group.
[03:47.87]Another key element is to be aware of the type of questions you ask.
[03:52.87]In order to make sure that participants don't search for what they think is the perfect answer, always ask open questions.
[04:02.15]For example, what would you do differently next time?
[04:06.37]Ensure that every member of the team has the chance to speak.
[04:11.94]It's also important to make sure you write down the specific recommendations made by everyone, but don't forget to pass this information on to non-participating team leaders, so that they too can learn from the experience.
[04:27.06]This is how after action reviews contribute to organization-wide learning and improvement.
[04:34.38]However, if no one follows up on these recommendations, then the process is wasted.
[04:40.62]You should also ensure that the ideas from the after action review are incorporated into your business by organizing staff training around them.
[04:51.30]Finally, the last thing you want is to find that you don't get through everything, because you've been talking too much, so make sure you keep a constant eye on the time.
[05:02.55]After action review is not something that you should ever plan on conducting in two sessions.
[05:08.83]Now, before we go on to look at the next type of project review...

Question 31-40
收藏
反馈
笔记
我的笔记
5000
保存

Write ONE WORD ONLY for each answer

After-Action Review Process

Background

A way of evaluating during a project in order to make improvement

Developed by the

Benefits

Not just for large projects, can also be used after.

l a staff meeting

l a 32incident

Develops better team communication because of the emphasis on 33

What is an After-Action Review

It's a meeting that.

l concentrates on results and the 34 from them

l encourages participation

l stresses the need to 35each other

Things to remember when conducting an After Action

Review

l Use an external facilitator

l To encourage participation, get the group's thoughts in 36

l Remember to use 37questions.

l Give any recommendations to other team 38______

l Make sure you follow up on ideas and provide 39______for employees

l Remember to check the 40often